Construction work is progressing actively at Samgori Tower

18 July, 2025

Construction work is progressing actively at Samgori Tower

Construction works at Samgori Tower are actively progressing.

Four floors of the project have already been built:


▪️ The foundation pouring and the slab works for both parking levels have been completed;
▪️ The slab works for the first commercial floor have also been completed.

 

At this stage, the construction of the columns for the second commercial floor is actively underway.

 

Learn more about the project: